IDOT CONTRACT 62H49

LA GRANGE ROAD BRIDGE OVER THE ICG (CN) RAILROAD, I&M CANAL AND CHICAGO SANITARY AND SHIP CANAL
  • The improvement consists of: 
    • Removal and replacing the existing bridge decks with a new PCC deck which will provide three 11’ wide lanes with 3’-8” wide inside and outside shoulders.
    • Lighting system replacement on both northbound bridges
    • Piers repairment
    • Staged construction will be utilized to close the northbound structures and northbound and southbound traffic will share the existing southbound lanes during construction.