IDOT CONTRACT 60956 & 60957

US ROUTE 45 RECONSTRUCTION PROJECT FROM IL 137 TO WASHINGTON STREET

Tecma served as the prime consultant on this $22 million project

  • Improvement consisted of:
    • Reconstruction and widening of over 4 miles of US 45 from a 2-lane cross section to a 5-lane section utilizing jointed PCC pavement
    • Installing new closed drainage system
    • Utilizing Lightweight Cellular Fill in lieu of Aggregate Base over soft compressible soils at Washington Street intersection
    • Installation of new interconnected traffic signals
    • Construction of new overflow ditch for Gages Lake

 

TECMA RECEIVED THE IDOT 2012 STATEWIDE DBE AWARD FOR EXCEPTIONAL PHASE III CONSULTING ENGINEERING SERVICES FOR THIS PROJECT