IDOT – Taylor St. Bridge Reconstruction Over 90/94, Jane Byrne (Circle) Interchange

Tecma served as the Prime Consultant providing Phase III Construction Engineering Services for this $19 Million project, which was completed in the Spring of 2017. The project included removal and replacement of the existing Taylor Street Bridge, retaining wall construction, hydro-scarification/latex overlay of the Taylor Street entrance ramp to NB 90/94, painting of the Roosevelt Road Bridge over 90/94 and Taylor entrance ramp, new traffic signals/lighting/ITS, roadway reconstruction, drainage work, sidewalk/C&G/driveway reconstruction, landscaping, signage, and pavement marking installation.

Project challenges included maintaining safe traffic flow on arterial streets & 90/94, and extensive coordination with abutting Circle Interchange contracts, ComEd, OEMC, CDOT, CDOWM, and UIC.